Clarington Underserved Broadband Internet Program
The challenge. A rural broadband program crossing some of the most heavily regulated ground in Ontario: 35 major national pipeline crossings, 8 railway crossings, 2 provincial highway crossings and more than 20 watercourse crossings — each with its own authority, permit and conditions.
Our approach. Every crossing was designed and permitted by our own team before a rig arrived — pipeline crossing agreements, rail applications, MTO encroachment permits and conservation-authority approvals in parallel, so construction never waited on paper.
Delivered. 100 km of 12-way and 110 km of 24-way microduct, 20 km of 4-in duct, 6 km of 6-in duct — over 1,300 homes passed. Over 157,000 m installed in a six-month construction season by our own crews.